Earned Value Calculator

Enter BAC, PV, EV, and AC. Get CPI, SPI, EAC, ETC, TCPI, VAC, and project health assessment instantly. Built for PMP® and PMI-SP® aspirants and working project controls professionals.

Project inputs

All four values in the same currency and unit. Use any consistent scale.

Cost display currency (calculation is unit-agnostic)
Total approved project budget.
Value of work planned to be complete by the status date.
Value of work actually completed by the status date.
Money actually spent to complete the work done.

Results

Metrics update the moment you press Calculate.

Enter values on the left, then Calculate.

Formulas used

CV = EV − AC
SV = EV − PV
CPI = EV ÷ AC
SPI = EV ÷ PV
EAC = BAC ÷ CPI   (assumes current CPI continues)
ETC = EAC − AC
VAC = BAC − EAC
TCPI = (BAC − EV) ÷ (BAC − AC)